PROJECTS EXPERIENCE

PBL Block.jpg
KEPALA BURUNG BLOCK TERMINATION - PETROGAS (BASIN) LTD.  
2019 - 2020​
​

Kepala Burung is PSC block in Papua Barat which is operated by Petrogas (Basin) Ltd. since 2016. In 2020 the block will be terminated as stipulated on the PSC contract. Termination team is cross function from various section

​

Logistics as part of termination team already started in 2019 to prepare asset hand over arrangement to SKK Migas. 15 October 2020 started to gross split scheme. 

Salawati block.jpg
SALAWATI BLOCK TAKE OVER      PETROGAS (ISLAND) LTD.
2019 - 2020
​

In 2020 Salawati Block in Papua Barat that operated by JOB Pertamina - Petrochina will be terminated and hand over to Petrogas (Island) Ltd as new operator. Handover process already started in 2019 until 2020. Logistics conduct some tasks such as asset handover, material transaction migration and ERP - JDE Implementation.

​

The project already completed in April 2020 and have successfully operated.

JDE.jpg
EAM (Enterprise Asset Management) MODULE JD EDWARDS IMPLEMENTATION PETROGAS (BASIN) LTD.
2020
​

The project aims to enhance maintenance schedule for equipment and engine especially inline spare parts availability. The project team consist of IT, maintenance, logistics and accounting. Logistics conduct determine BOM (Bill of Material), created material supply contract, lead time arrangement, created material codification and arrange material master on JDE.

​

The project started in January 2020 and  completed in June 2020 and have successfully operated.

20180630_181347_HDR-1.jpg
DRILLING PROJECT
PETROGAS (BASIN) LTD.
2019​
​

In 2019 Petrogas (Basin) Ltd. started drilling for well development. There are 2 wells consists of Walio 318 and 319. Logistics were responsible to provide material including mob and demob. Also ensure no delay time in delivery.

​

The project was completed and have successfully.

FLNG PROJECT 7.5 MTPA
INPEX MASELA LTD.
2014 - 2016
​

Joining in SCM Division in 2014. Involve in Logistics and Material Management Projects such as prepare Logistics Base, Material Management flow and design and Warehousing.

​

The project was reschedule due to any changes to built in onshore. 

​
inpex1.jpg
medco1.jpg
VARIOUS PROJECTS
PT MEDCO E&P INDONESIA
2006 - 2014
​

Joining in SCM Division in 2006. Have been involve in many projects such as EPC, SAP Customization, ISRS7 (HSEQ System), TAC Tarakan & Sembakung Block Termination, EOR, Drilling and so on.

bottom of page